Agenda Item # 11.C.
City Commission Regular Meeting - 5:05 PM
Meeting Date:
06/01/2026
Re
Approval of Ferreira Construction Deduct CO No. 1 - Indian River Drive Corridor Improvements - Bid No. 2025-019
Submitted For:
Mark Zrallack

SUBJECT:

Approval of Ferreira Construction Change Order No. 1 in the amount of negative $226,261.52; a net savings of $55,873.72 after a direct material purchase from FPUA on the Indian River Drive Roadway Reconstruction project.

SUMMARY:

The Indian River Drive Roadway Reconstruction project improvements include street lighting materials at a cost of $226,261.52.  As part of the Engineering Department's efforts to provide project cost savings, we coordinated with FPUA for the direct purchase of street lighting materials at a cost of $170,387.80.  This direct material purchase will provide a total cost savings of $55,873.72 to the City of Fort Pierce.   

RECOMMENDATION:

Staff recommends approval of deduct Change Order No. 1.

ALTERNATIVES:

Deny and forfeit the $55,873.72 cost savings.

RESPONSIBLE STAFF:

Engineering

COORDINATED WITH:

Fort Pierce Utilities Authority
Ferreira Construction Company, Inc.

Fiscal Impact

Budgeted Y/N:
Y
Fiscal Year:
FY 25/26
Account:
3127700-563100
Amount:
-226,261.52

FISCAL IMPACT:

Deduction of ($226,261.52) from the previously approved $10,254,124.04 Indian River Drive construction contract. Ref. Bid No. 2025-019, PO No 26-0391, Project Code IRDCI.