Approval of Kimley-Horn & Associates CO No. 1 (SA No. 1) - Surfside Residential Park Drainage Improvements Phase II- Ref. RFQ No. 2025-022
Submitted For:
Mark Zrallack

SUBJECT:

Approval of Kimley-Horn & Associates Change Order No. 1 to Specific Authorization No. 1 for an amount not to exceed $69,023.50 for the Surfside Residential Park Drainage Improvements - Phase II CEI Services. 

SUMMARY:

Field conditions such as underground utility conflicts, abandoned and buried infrastructure led to unforeseen field changes or re-design. Field changes were compounded by supply delays for material purchase or fabrication with long lead times. This further led to schedule impacts. As a result, additional time is necessary for the construction phase inspection and testing required for the completion of Surfside Phase II Construction Project. 

RECOMMENDATION:

Staff recommends approval.

ALTERNATIVES:

Deny and contract with another consultant. This action will delay construction completion. 

RESPONSIBLE STAFF:

Engineering Department

COORDINATED WITH:

Kimley-Horn and Associates
City Attorney's Office

Fiscal Impact

Budgeted Y/N:
Y
Fiscal Year:
26/27
Account:
4034300-534900
Amount:
$69,023.50

OTHER INFORMATION:

The $69,023.50 will be funded from the City's Stormwater Management Utility Account No. 4034300-534900.