Agenda Item # 10.e.
City Commission Regular Meeting
Meeting Date:
12/05/2016
Re
Accept Request for Chiller Replacement/Bid No. 2016-033 Sunrise Theatre
Submitted For:
John Wilkes

SUBJECT:

Accept Bid No. 2016-033 for Chiller Replacement Sunrise Theatre to Gibson Air Conditioning & Refrigeration, LLC in the amount of $96,285.

SUMMARY:

Since reopening in 2006, the Sunrise Theatre has the two original chillers for the facility. During the past year, Chiller #1 has been operating at 50 percent or less capacity.  Not only does this create a temperature problem for patrons, but the extra operational demand on Chiller #2 is compromised by this situation.  As a result, the equipment is not operating at full capacity and has consistent maintenance issues. Current circumstances also require both chillers to run almost constantly.  Replacing Chiller #1 would allow a return to almost normal operation with only one operating  resulting in an energy savings.

RECOMMENDATION:


Accept Request for Chiller Replacement/Bid No. 2016-033 Gibson Air Conditioning & Refrigeration, LLC in the amount of $96,285.

ALTERNATIVES:

Seek additional bids to complete the chiller replacement task.

RESPONSIBLE STAFF:

John Wilkes, Executive Director, Sunrise Theatre

COORDINATED WITH:

Gelencia Carter, Purchasing Manager
Georgia Montgomery, Purchasing Specialist

Fiscal Impact

Budgeted Y/N:
N
Fiscal Year:
2016/17
Account:
40646005756320
Amount:
96,285

OTHER INFORMATION:

A new Restoration Service fee of $3.00 per ticket has been implemented this fiscal year to provide funding for the new chiller and any other capital expenditures at the Sunrise Theatre.

Attachments

Form Review

Inbox Reviewed By Date
Finance Department Karen Logue 11/29/2016 05:10 PM
City Manager Nick Mimms 11/29/2016 05:21 PM
Form Started By:
asatterlee
Started On:
11/17/2016 01:13 PM
Final Approval Date:
11/29/2016