Agenda Item # 9.a.
City Commission Regular Meeting
- Meeting Date:
- 02/18/2014
- Re
- Approval of Specific Authorization No. 17 to Tetra Tech, Inc
- Submitted For:
- John Andrews
SUBJECT:
Approve Specific Authorization No. 17 to Tetra Tech, Inc. of Stuart Florida for construction engineering services for the City Marina Reconstruction Phase II in the amount of $997,272.00.
SUMMARY:
Tera Tech will assist the City with construction administration, engineering review, construction calculation reviews, testing, site compliance monitoring and project closeout.
RECOMMENDATION:
Approval
ALTERNATIVES:
Reject the proposal and solicit a new engineering firm.
RESPONSIBLE STAFF:
Edward Seissiger, Project Coordinator
COORDINATED WITH:
Brian Procter and Stuart McGahee with Tetra Tech, Inc
Fiscal Impact
- Budgeted Y/N:
- N
- Fiscal Year:
- 2014
- Account:
- 401-4100-575-6360
- Amount:
- $997,272.00
OTHER INFORMATION:
This item will be funded by the Marina Enterprise Fund and reimbursable by FEMA under FEMA project 438.
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| City Manager | rbradshaw | 01/27/2014 03:24 PM |
| Finance Department | gjohnson | 01/27/2014 03:29 PM |
| City Manager | rbradshaw | 01/27/2014 03:30 PM |
- Form Started By:
- eseissiger
- Started On:
- 01/22/2014 12:06 PM
- Final Approval Date:
- 01/27/2014