Agenda Item # 13.a.
City Commission Regular Meeting
- Meeting Date:
- 01/22/2019
- Re
- FDOT Joint Participation Agreement (JPA) Amendment No. 2 - Ohio Avenue and US Highway 1 Intersection Improvements
- Submitted For:
- John Andrews
SUBJECT:
Resolution 19-R03 authorizing the execution of FDOT's JPA Amendment No. 2 which provides additional project funding in the amount of $100,000.
SUMMARY:
The original JPA provided project funding in the amount of $150,000 to compensate for construction costs associated with the proposed intersection improvements to Ohio Avenue and US 1. These improvements include the realignment of the skewed east-west legs of the intersection, installation of three (3) mast arms complete with associated traffic signal equipment. The total State project reimbursement of $250,000 towards the estimated $506,000 intersection construction cost is proposed. This does not include the cost of the proposed improvements to Ohio Avenue between US 1 and 3rd Street which is estimated at $509,000.
RECOMMENDATION:
Staff recommends approval
ALTERNATIVES:
Deny and leave intersection as is
RESPONSIBLE STAFF:
Engineering
COORDINATED WITH:
FDOT
Fiscal Impact
- Budgeted Y/N:
- N
- Fiscal Year:
- FY 19/20
- Account:
- TBD
- Amount:
- $505,741.40
FISCAL IMPACT:
Total intersection construction cost of $505,741.40 will have a $250,000 reimbursement by the State leaving $255,741.40 to be compensated by the City.
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Finance Department | Johnna Morris | 01/14/2019 05:24 PM |
| City Manager | Nick Mimms | 01/16/2019 12:56 PM |
- Form Started By:
- Tracy Telle
- Started On:
- 01/02/2019 08:20 AM
- Final Approval Date:
- 01/16/2019