| June 9, 2015 |
There was a structure fire that caused significant damage |
| August 3, 2015 |
Demolition application submitted |
| August 10, 2015 |
Complainant alleges demolition commenced by Port St. Lucie (PSL) Properties |
| August 12, 2015 |
Condemnation report mailed and Unsafe Building Affidavit recorded with Clerk of Court |
| September 16, 2015 |
Contract was entered into for the rehabilitation of the structure |
| September 17, 2015 |
A revision was submitted to the demolition permit to include roof, trusses, shingles, drywall, 8 floor joists, and two (2) partial exterior walls. |
| September 22, 2015 |
The revision was approved by the Building Department. |
| September, 2015 |
The attorney for PSL Properties alleges that PSL Properties was hired to repair the property once demolition of the damaged areas of the home was completed by a different contractor. It is also noted that the first contractor hired did not complete demolition and demolition had to be completed by PSL Properties. |
| November 19, 2015 |
A rehabilitation permit was submitted. |
| November 21, 2015 |
The demolition permit expired without having the required inspections |
| December 7, 2015 |
The rehabilitation permit was approved by the Building Department and ready for pick up. |
| December 15, 2015 |
The complainant alleges that this was the date that the contractor filed for the rehabilitation permit; the is actually the date that the rehabilitation permit was issued. It should also be noted that the permit was not issued in November as the attorney for PSL Properties indicated in their response. It is unclear when the rehabilitation work began. |
| December 31, 2015 |
Courtesy, framing, sheathing, tie down, roof sheathing, and wind brace inspections were conducted thus indicating work commenced prior to this date. |
| January 7, 2015 |
A roof dry in inspection was conducted and approved with the exception of missing flashing in the valley. It was not indicated by either party by either party when the owner decided to have a metal roof installed instead of a shingle roof. |
| January 26, 2016 |
A revision was submitted for the change of roof material. |
| January 28, 2016 |
The revision was approved by the Building Department. |
| April 12, 2016 |
Building Department received Contractor Complaint against PSL Properties |
| April 13, 2016 |
Notice of Probable Cause/ Hearing sent to Respondent. |
| August 9, 2016 |
Item is heard by the Board of Examiners of Contractors and is Continued until after the pending Civil hearing. |
| April 12, 2019 |
Request was made by the complainant to bring this matter back in front of the board. |
| April 12, 2019 |
Ms. Comask renewed the permit stating that all of the work had been completed. However, final inspections were not completed. |
| April 23, 2019 |
Notice of Hearing sent to Mr. Petruzzelli and the Complainant. |
| April 15, 2019 |
All required final inspections were approved and the permit was closed. |
| May 14, 2019 |
Item to be heard at the Board of Examiners of Contractors meeting. |