Agenda Item # 11.g.
City Commission Regular Meeting
- Meeting Date:
- 06/03/2019
- Re
- Dreamland Park - Parking Improvements - Final Chage Order, Bid No. 2016-016
- Submitted For:
- John Andrews
SUBJECT:
Approval of Final Change Order in the amount of $3,258.75, bv C.W. Roberts Contracting, Inc. for parking improvements at Dreamland Park in conjunction with the "Wall of Remembrance" project.
SUMMARY:
This change order is necessary for the final closeout of the project. The change order amount, $3,258.75 was the fee for the building permit, which was not part of the original contract proposal.
RECOMMENDATION:
Recommend approval of Change Order No. 7 to C.W. Roberts Contracting Inc.
ALTERNATIVES:
Pay building permit fees directly.
RESPONSIBLE STAFF:
Desmond Sumner, Engineering
COORDINATED WITH:
N/A
Fiscal Impact
- Budgeted Y/N:
- N
- Fiscal Year:
- 2018/2019
- Account:
- 100-1111-519-6310
- Amount:
- $3,258.75
FISCAL IMPACT:
Change order will be funded by Parks MSBU Account No. 100-1111-519-6310.
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Finance Department | Johnna Morris | 05/24/2019 11:23 AM |
| City Manager | Nick Mimms | 05/24/2019 04:56 PM |
- Form Started By:
- jandrews
- Started On:
- 05/22/2019 01:37 PM
- Final Approval Date:
- 05/24/2019