SUBJECT:

Progress Payment #11 is in the amount of $657,728.27 is due to PCN3 Inc of Los Alamitos, CA for City of Hawthorne New Senior Center (Project #24-03).
 

RECOMMENDED MOTION:

Staff recommends that the City Council approve this Progress Payment #11 to PCN3 Inc of Los Alamitos, CA

DISCUSSION:

This project includes providing all services, labor, materials, permits, insurance, tools and equipment needed, in accordance with the Plan and Specifications to successfully and safely complete the renovations and addition to the existing Senior Center.

The work will consist of renovating the existing Hawthorne Senior Center situated on the northwest side of the existing Memorial Center facility. The renovations will bring the existing building, approximately 8,600 SF, up to current building codes and standards. The work will also consist of adding a first-floor extension and a second story, approximately 9700 SF of indoor space. There will also be some exterior landscaping to integrate the building into the park and create an outdoor courtyard. The work will also consist in providing all services, labor, materials, permits, insurance, tools and equipment needed, in accordance with the Plan and Specifications to successfully and safely complete the renovations, expansion and addition to the City of Hawthorne Senior Center located at 3901 El Segundo Blvd, Hawthorne, CA 90250

During the construction phase of the project, necessary authorization will need to be granted to the City’s Project Engineer(s) to conduct further testing, substitutions, and/or removal of materials such as new public right of way, new concrete slab between the New Senior Center and existing Memorial Center, etc.  

The first floor room framing (aluminum frame) is underway and should be completed by March. Exposed ABS plumbing pipes are being replaced with cast iron, so no accidental future damage can be caused. The contractor is currently working on interior duct work for the new HVAC system and working on restroom plumbing installations. The 2nd floor slab was placed and wooden/metal beams for the roof are being placed, welded and inspected. Staircase #1 has been welded and will be installed on site by mid-February and staircase #2 will be installed by the first week of March the latest. 

 

ECONOMIC DEVELOPMENT STRATEGIC PLAN:

This project is a result of the City working closely with funding and regulatory agencies to support and improve our infrastructure.

 

FISCAL IMPACT:

None. Funds for this progress payment in the amount of $657,728.27 will be funded through allocated funds from the 2024-2025 budget.