AGENDA ITEM NO. 13.
CITY OF HAWTHORNE City Council AGENDA BILL For the meeting of 11/12/2024 Originating Department: Public Works |
City Manager:
Department Head:
SUBJECT:
Progress Payment #4 and #5 in the amount of $929,286.20 due to DOJA, Inc. of Ontario CA for Zela Davis Park Renovation (Project #24-04)
RECOMMENDED MOTION:
Staff recommends that the City Council approve this Progress Payment #4 and #5 and approve Change Order #1 to DOJA, Inc. of Ontario, CA.
DISCUSSION:
This project involves enhancing Zela Davis Park, a 0.5-acre underutilized park in the City of Hawthorne. The initiative aims to transform the existing space into a versatile, climate-resilient community area. This will be achieved through the installation of a new playground, a picnic area featuring shade structures, exercise equipment, a half court, walking paths adorned with mosaic art elements, perimeter fencing, restroom building, California native plants, bioswale, and various sustainable elements. All activities will be conducted in accordance with the specified Plans and Specifications to ensure the successful completion of the improvements.
Current progress consists of improving site sewer, water, drainage and pipe installation work. In addition, construction of curb and gutter, pedestrian walkway and sidewalk, installation of bioswale, installation of new playground and shade sail, continued construction of restroom building, construction of fencing and gates, installation of site electrical, lighting and security and installation of irrigation. Change Order #1 provides design changes to the shade sail structure to provide a wider range of shaded area. Also, an addition of drywall to enhance stormwater drainage system.
Current progress consists of improving site sewer, water, drainage and pipe installation work. In addition, construction of curb and gutter, pedestrian walkway and sidewalk, installation of bioswale, installation of new playground and shade sail, continued construction of restroom building, construction of fencing and gates, installation of site electrical, lighting and security and installation of irrigation. Change Order #1 provides design changes to the shade sail structure to provide a wider range of shaded area. Also, an addition of drywall to enhance stormwater drainage system.
ECONOMIC DEVELOPMENT STRATEGIC PLAN:
This project is a result of the City working closely with funding and regulatory agencies to support and improve our infrastructure. This project will enhance the quality of life in the City, creating publicly accessible and usable open space.
FISCAL IMPACT:
None. Funds for this progress payment in the amount of $929,286.20 are available in the adopted Fiscal Year 2024-2025 budget and will be paid for with approved and allocated funds through grants from the State of California Department of Transportation, Clean California Local Program, County of Los Angeles Measure A, and Baldwin Hills Urban Watersheds Conservancy (funded under Proposition 40)
NOTICING PROCEDURE:
72 hours posted notice pursuant to the Ralph M. Brown Act