AI- 101016
Purchasing Department 13.E.4.
CC CONSENT AGENDA SPECIAL MTG
Prct. 4
- Meeting Date:
- 10/14/2025
- Submitted For:
- Ignacio Amezcua
- Submitted By:
- Cassandra Carr
- Department:
- PURCHASING DEPT.
Information
CAPTION
Requesting acceptance and approval of Change Order No. 2 from Saenz Brothers Construction, LLC, for the "J-01 Stormwater Management Project" (C-24-0337-10-29) to reflect an additional 120 calendar days beyond the original contract completion date, as recommended by the Engineering firm TEDSI Infrastructure Group.
BACKGROUND
Unforeseen utility conflict with Vexus (new install) on March 19, 2025. Operations halted for redesign.
Fiscal Impact
- CALENDAR YEAR:
- 2025
- ACCT. #:
- 5-1200-431-00-124-007-0-723
- FUNDS AVAILABLE Y/N?:
- Y
- MATCHING FUNDS Y/N?:
BUDGETARY IMPACT:
Funds available as of 9/30/2025.Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Purchasing / Internal | Ignacio Amezcua | 10/03/2025 02:53 PM |
| Budget and Management | Melannie Rivera | 10/03/2025 02:56 PM |
| Final Approval | Monica Salinas | 10/07/2025 02:49 PM |
- Form Started By:
- Cassandra Carr
- Started On:
- 09/30/2025 04:20 PM
- Final Approval Date:
- 10/07/2025