CAPTION
Requesting approval of Change Order No.2, reflecting an increase in the amount of $91,080.00 and 60 additional calendar days for the project 'PD Lateral Extension 5 - 2023 Bond Referendum Project No. 15'', Contract No. C-HCDD1-25-015-06-24, with Synergy Development & Construction LLC, as recommended by Project Engineer, Izaguirre Engineering Group LLC.