CAPTION
Requesting acceptance and approval of Change Order No. 2 from 8/A Builders, LLC, for the "Palmer Pavilion Park Improvement Project" (C-25-0235-04-15) to reflect an additional 120 calendar days beyond the original contract completion date, as recommended by the Engineering firm B2Z Engineering.
BACKGROUND
Project No. 25-0235
C-25-0235-04-15