AI - 102718
5.B.
DD-CONSENT AGENDA SPECIAL MTG
- Meeting Date:
- 03/17/2026
- Submitted For:
- Omar Anzaldua Jr.
- Submitted By:
- Justin Silva
- Department:
- DRAINAGE DISTRICT
Information
CAPTION
Ratification of approved and fully executed Change Order No.1, reflecting an increase in the amount of $17,612.00 and an additional 181 construction calendar days for the project ''West Main Drain III Phase 1 -2023 Bond Referendum Project No. 14'', Contract No. C-HCDD1-24-061-12-17, with Econ Group, LLC, as recommended by Project Engineer, Assistant District General Manager, Omar Anzaldua Jr., PE, CFM, PMP, CCM and approved by District General Manager, Raul E. Sesin, PE, CFM.
BACKGROUND
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Final Approval | Nora Cavazos | 03/11/2026 02:50 PM |
- Form Started By:
- Justin Silva
- Started On:
- 03/06/2026 01:37 PM
- Final Approval Date:
- 03/11/2026