AI- 102785
Purchasing Department 20.C.4.
CC REGULAR AGENDA SPECIAL MTG
Prct. 2
- Meeting Date:
- 03/17/2026
- Submitted For:
- Eddie Cantu
- Submitted By:
- Erika Zamora
- Department:
- COMM. PCT. #2
CAPTION
A. Requesting approval of Supplemental Agreement No. 2 for services under Work Authorization 2 (C-21-0819-11-16) with B2Z Engineering, LLC, to amend Attachment A, B, and C to include the required design for the temporary traffic signal at the proposed West entrance of the courthouse square related to the Construction Management Services for Phase II Project - Courthouse Demolition and Other Services in the total amount of $59,370.16
B. Pursuant to Article 15 of the professional services agreement with B2Z Engineering, LLC, requesting authority for B2Z Engineering, LLC engage ETSI Group, LLC as a subcontractor.
B. Pursuant to Article 15 of the professional services agreement with B2Z Engineering, LLC, requesting authority for B2Z Engineering, LLC engage ETSI Group, LLC as a subcontractor.
BACKGROUND
Increase to Work Authorization No. 2 in the amount of $59,370.16.
Fiscal Impact
- CALENDAR YEAR:
- 2026
- ACCT. #:
- 1XXX-19-125-000-0000-507300
- FUNDS AVAILABLE Y/N?:
- Y
- MATCHING FUNDS Y/N?:
- N
BUDGETARY IMPACT:
Fund 1357 and Fund 1359 have funding available to fund Supplemental Agreement No. 2 to Work Auth 2 in the amount of $59,730.16.Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Purchasing / Internal | Olga Garza | 03/11/2026 04:49 PM |
| Budget and Management | Melannie Rivera | 03/11/2026 04:51 PM |
| Final Approval | Monica Salinas | 03/11/2026 04:58 PM |
- Form Started By:
- Erika Zamora
- Started On:
- 03/11/2026 12:54 PM
- Final Approval Date:
- 03/11/2026