Information

CAPTION

Requesting approval of Change Order No. 3 (C-25-0063-04-01) with RBM Contractors, LLC for the Hidalgo County Precinct 2 — Recreational Trails Connectivity Project - Mission Segment 2, as recommended by project manager, Stanley Ramos, with authority for Commissioner Eduardo "Eddie" Cantu to sign the approved change order. (ARPA-21-122-040)

BACKGROUND

Request for contract increase in the amount of $58,924.92 to remove existing riprap, excavation (junc. box & rcp), 5'X5' junction box, 36" rcp, riprap (conc.) (5"), energy dissipators, bedding (gravel), cement stabilized backfill.  Requesting an additional 50 days due to Design & Modification.  Resulting in a new contract expiration date of 09/05/26

Fiscal Impact

CALENDAR YEAR:
2026
ACCT. #:
1290-52-115-000-0000-507400
FUNDS AVAILABLE Y/N?:
Y
MATCHING FUNDS Y/N?:
N

BUDGETARY IMPACT:

N/A

Attachments

Form Review

Inbox Reviewed By Date
Final Approval Margaret Mungia 05/06/2026 04:49 PM
Form Started By:
Lupita Garza
Started On:
05/04/2026 03:23 PM
Final Approval Date:
05/06/2026