AI - 103381
7.D.
DD-REGULAR AGENDA SPECIAL MTG
- Meeting Date:
- 05/12/2026
- Submitted For:
- Yvette Barrera
- Submitted By:
- Justin Silva
- Department:
- DRAINAGE DISTRICT
Information
CAPTION
Requesting approval of Change Order No. 3, reflecting an increase in the amount of $252,516.90 and 90 additional construction calendar days for the project "Hidalgo Drain Drainage Improvement - 2018 Bond Referendum Project No. 13", Contract No. C-HCDD1-24-034-08-06, with RDH Site and Concrete, LLC, as recommended by Project Engineer, SAMES, Inc.
BACKGROUND
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Final Approval | Nora Cavazos | 05/06/2026 03:29 PM |
- Form Started By:
- Justin Silva
- Started On:
- 05/06/2026 10:31 AM
- Final Approval Date:
- 05/06/2026