CAPTION

Presentation for discussion, consideration, acceptance and approval "Certificate of Completion" submitted by Closner Construction in connection with contract #C-08-320A-12-02/PO#616234 for: Construction Services for Repair, Reconstruction of Culvert Pipe Bridge at Mile 3 North and FM 491 and thus permitting the issuance of payment by the County Treasurer of Invoice #1 in the amount of $134,887.50 (approved by CC on 4-7-09 and subject to processing procedures by the  County Auditor).   

BACKGROUND

Request for payment had been previously submitted and approved by CC on 04/07/09.  Payment has not been initiated until the "Certificate Of Construction Completion" is submitted.

Fiscal Impact

FISCAL YEAR:
2009
ACCT. #:
9-1201-431-00-121-052-0-733
FUNDS AVAILABLE Y/N?:
Y
MATCHING FUNDS Y/N?:

BUDGETARY IMPACT:

Amount available in PO #616234 $134,887.50, pending reclassificaiton of PO to program no. 005. Please refer to interdept transfer AI #15146.

Attachments

Form Review

Inbox Reviewed By Date
Purchasing / Internal msalazar 04/23/2009 10:40 AM
Budget and Management Veronica Lopez 04/23/2009 11:25 AM
Auditor's Office 04/24/2009 05:37 PM
Form Started By:
vgarcia
Started On:
04/22/2009 04:33 PM
Final Approval Date:
04/24/2009