AI- 15220
15.E.1.
CC REGULAR
- Meeting Date:
- 05/05/2009
- Submitted For:
- Agapito Vargas
- Submitted By:
- Marcie Jackson, COLONIA ACCESS PROGRAM
- Department:
CAPTION
Presentation for discussion, consideration and action on a recommendation by project engineer Yzaguirre Engineering Group, LLC to award to the lowest bidder meeting all specifications for the following bids;
A. Bid No. CAP-2009-128-03-25-YSI Los Encincos I Subdivision
B. Bid No. CAP-2009-128-03-25-YSI Los Encinos II Subdivision
and approval of contract subject to legal review and TXDOT approval.
BACKGROUND
Fiscal Impact
- FISCAL YEAR:
- 2009
- ACCT. #:
- 9-1312-431-00-122-890-0-731/733
- FUNDS AVAILABLE Y/N?:
- Y
- MATCHING FUNDS Y/N?:
BUDGETARY IMPACT:
Obj. 731 & 733 have available balance of $71,104.48 as of 05/01/09.- FISCAL YEAR:
- 2009
- ACCT. #:
- 9-1312-431-00-122-891-0-731/733
- FUNDS AVAILABLE Y/N?:
- Y
- MATCHING FUNDS Y/N?:
BUDGETARY IMPACT:
Obj 731 & 733 have available balance of $183,411.67 as of 05/01/09.Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Purchasing / Internal | msalazar | 04/29/2009 05:23 PM |
| Budget and Management | Veronica Lopez | 04/30/2009 08:06 AM |
| Auditor's Office | 05/01/2009 05:28 PM |
- Form Started By:
- mjackson
- Started On:
- 04/28/2009 11:03 AM
- Final Approval Date:
- 05/01/2009