AI- 17086
23.C.2.
CC REGULAR
Meeting Date:
08/25/2009
Submitted For:
Marty Salazar
Submitted By:
Oscar Garza, PURCHASING DEPT.
Department:
PURCHASING DEPT.

Information

CAPTION

Request acceptance and approval of Contractor's Application for Final Payment #4 in the amount of $25,615.90 which includes retainage payable to Herrera & Hunt, Inc. for Project #2008-119-OGG as reviewed by auditors and pursuant to action taken on 07/28/09 regarding project completion forms as requested by Texas Parks & Wildlife have been approved.

BACKGROUND

Pursuant to action taken on 07/28/09 (AI - 16633) items a, b & d were approved pending review and correction to Schedule of Value; as reviewed by Mike Escaname from Auditors Office documentation is in order.

Fiscal Impact

FISCAL YEAR:
2009
ACCT. #:
9-1287-452-00-123-043-9-739
FUNDS AVAILABLE Y/N?:
Y
MATCHING FUNDS Y/N?:
N

BUDGETARY IMPACT:

Available funds in P.O. #606377 as of 8/21/09 is $5,078.00.







FISCAL YEAR:
2009
ACCT. #:
9-1287-206-00-000-002-0-000
FUNDS AVAILABLE Y/N?:
Y/Pending
MATCHING FUNDS Y/N?:
N

BUDGETARY IMPACT:

Current available balance in retainage is $21,422.90; After final payment of $4,193.00 ($419.30 retainage) total retainage will be $21,842.20.

Attachments

Form Review

Inbox Reviewed By Date
Purchasing / Internal msalazar 08/20/2009 04:56 PM
Budget and Management Erika Zamora 08/21/2009 08:39 AM
Auditor's Office 08/21/2009 05:32 PM
Form Started By:
Olga Garza
Started On:
08/20/2009 03:45 PM
Final Approval Date: