Skip to main content

AgendaQuick™

View Agenda Item

AI- 17128
23.G.3.
CC REGULAR
Meeting Date:
09/01/2009
Submitted For:
Agapito Vargas
Submitted By:
Marcie Jackson, COLONIA ACCESS PROGRAM
Department:

Information

CAPTION

Acceptance, and approval of Application for payment No. 3 (Release of Retainage) in the amount of $10,503.60 from Valley Paving Inc. contracted vendor for El Monte Subdivision, submitted by project engineer TEDSI Infrastructure Group, CAP 08-032-03-31.

BACKGROUND


Fiscal Impact

FISCAL YEAR:
9
ACCT. #:
9-1311-206-00-000-019-0-000
FUNDS AVAILABLE Y/N?:
Y
MATCHING FUNDS Y/N?:

BUDGETARY IMPACT:

Project has been completed and P.O.# 621820 has been paid in full.

available balance of retainage payable for Valley Paving, Inc. is $15,522.73 as of 8/28/09.

Attachments

Form Review

Inbox Reviewed By Date
Purchasing / Internal msalazar 08/27/2009 12:59 PM
Budget and Management Erika Zamora 08/27/2009 02:31 PM
Auditor's Office 08/28/2009 06:09 PM
Form Started By:
mjackson
Started On:
08/25/2009 08:51 AM
Final Approval Date:
08/28/2009