a. Acceptance and approval of Application for Payment (Release of Retainage) in the amount of $1,513.95 from Homer Alvarez d/b/a Alvarez Construction in connection with Red Barn Subdivision project, as submitted by R. Gutierrez Engineering Corporation-C-CAP-09-002-04-21;

b. Requesting approval of "Certificate of Construction Completion" submitted by project R. Gutierrez Engineering Corporation reflecting the completion date of June 12, 2009 for Red Barn Subdivision-C-CAP-09-002-04-21.

BACKGROUND


Fiscal Impact

FISCAL YEAR:
9
ACCT. #:
9-1311-206-00-000-020-0-000
FUNDS AVAILABLE Y/N?:
Y
MATCHING FUNDS Y/N?:

BUDGETARY IMPACT:

A. Amount available in retainage account is $1,448.95, plus $65.00{retainage from Final Pymt, AI-17151 CC 09/01/09} = $1,513.95

B. Amount owed is {Final Pymt $585.00 + Retainage $1,513.95} = $2,098.95

Attachments

Form Review

Inbox Reviewed By Date
Purchasing / Internal msalazar 08/27/2009 01:05 PM
Budget and Management Erika Zamora 08/27/2009 02:35 PM
Auditor's Office 08/28/2009 06:09 PM
Form Started By:
mjackson
Started On:
08/26/2009 09:32 AM
Final Approval Date: