CAPTION

Acceptance and approval of Change Order No. 1 with contractor Closner Construction for Ramon Leal Subdivision, Pct. No. 3 reflecting a decrease in the amount of $1,875.00 since utility adjustments were deleted and submitted through project engineer Izaguirre Engineering Group, LLC (C-CAP 09-132-06-08).

BACKGROUND


Fiscal Impact

FISCAL YEAR:
2009
ACCT. #:
9-1XXX-431-00-123-591-0-73X
FUNDS AVAILABLE Y/N?:
Y
MATCHING FUNDS Y/N?:
N

BUDGETARY IMPACT:

Change Order will decrease P.O. #627746 in the amount of $1,875.00 leaving the P.O. with a balance of $91,292.06.
Please refer to attached P.O. #627746.

Attachments

Form Review

Inbox Reviewed By Date
Purchasing / Internal msalazar 11/12/2009 12:08 PM
Budget and Management Erika Zamora 11/12/2009 01:32 PM
Auditor's Office 11/13/2009 05:16 PM
Form Started By:
mjackson
Started On:
11/09/2009 02:36 PM
Final Approval Date:
11/13/2009