AI- 23619
27.B.4.
CC REGULAR
Meeting Date:
10/26/2010
Submitted For:
Yolanda Cisneros
Submitted By:
Yolanda Cisneros, COMM. PCT. #2
Department:
COMM. PCT. #2

Information

CAPTION

Requesting approval of Change Order No. 2 increase in of 18 calendar day with Total Commitment LLC(contracted vendor for “North Tower Road Crossing Drainage Improvement Project”) reflecting weather days, due to recent rains, ground conditions too wet to conduct work within the project area,  with authority for County Judge to execute document.

BACKGROUND

Contract #C-10-032-02-16 PO #637386

Fiscal Impact

FISCAL YEAR:
2010
ACCT. #:
0-1339-431-00-122-050-0-733
FUNDS AVAILABLE Y/N?:
Y
MATCHING FUNDS Y/N?:

BUDGETARY IMPACT:

*only calendar days have increased to a total of 155 calendar days. Contract Amount has not changed.

Attachments

Form Review

Inbox Reviewed By Date
Purchasing / Internal msalazar 10/22/2010 11:31 AM
Budget and Management Sylvia Solis 10/22/2010 01:06 PM
Auditor's Office lfong 10/22/2010 02:48 PM
Form Started By:
ycisneros
Started On:
10/21/2010 01:36 PM
Final Approval Date:
10/22/2010