AI- 23885
21.C.2.
CC REGULAR
- Meeting Date:
- 11/09/2010
- Submitted For:
- Yolanda Cisneros
- Submitted By:
- Yolanda Cisneros, COMM. PCT. #2
- Department:
- COMM. PCT. #2
CAPTION
Requesting approval of Change Order No.1 increase in the amount of $45,723.00 with D. Wilson Construction Co. (Contract #C-09-037C-11-17), in connection witht he "Construction of the New Precinct #2 Administration Office & Other County Offices", for the design and installation of sprinkler irrigation system.
BACKGROUND
Fiscal Impact
- FISCAL YEAR:
- 2010
- ACCT. #:
- 0-1200-431-00-122-021-0-739
- FUNDS AVAILABLE Y/N?:
- Y
- MATCHING FUNDS Y/N?:
BUDGETARY IMPACT:
AI-23884 11/09/10 (Additional transfer to cover contractor's fees)
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Purchasing / Internal | msalazar | 11/05/2010 04:08 PM |
| Purchasing / Internal | msalazar | 11/05/2010 04:08 PM |
| Budget and Management | Sylvia Solis | 11/05/2010 04:11 PM |
| Budget and Management | Sylvia Solis | 11/05/2010 04:11 PM |
| Auditor's Office | 11/05/2010 04:12 PM | |
| Auditor's Office | 11/05/2010 04:12 PM |
- Form Started By:
- ycisneros
- Started On:
- 11/05/2010 03:15 PM
- Final Approval Date:
- 11/05/2010