AI- 27956
15.D.1.
CC REGULAR
Meeting Date:
08/16/2011
Submitted For:
Marty Salazar
Submitted By:
Moises Salazar, PURCHASING DEPT.
Department:
PURCHASING DEPT.

Information

CAPTION

Requesting approval of Change Order No. 3 inceasing number of days for completion of project: "Hidalgo County Primary Care and Substance Abuse Facility Site and Utility Improvements", awarded to The 5125 Company Contract No. C-10-050-03-23 with authority for County Judge or Court Member to execute document.

BACKGROUND

Additional number of days consist of:
39 Rain Days
287 Work stoppage -holdig for other portions of project to be completed by County.
Total No. of additional days:  326.

Project Completion Date: September 8th, 2011.
 


Fiscal Impact

FISCAL YEAR:
2011
ACCT. #:
1-1100-415-00-115-002-0-841
FUNDS AVAILABLE Y/N?:
Y
MATCHING FUNDS Y/N?:

BUDGETARY IMPACT:

No Budgetary Impact.
PO No. 641069
Change Order # 3 - Time extension

Attachments

Form Review

Inbox Reviewed By Date
Purchasing / Internal msalazar 08/10/2011 11:47 AM
Budget and Management mmunoz 08/10/2011 01:33 PM
Auditor's Office aduran 08/11/2011 03:58 PM
Form Started By:
moysalazar
Started On:
08/09/2011
Final Approval Date:
08/11/2011