Urban County Program for Hidalgo County Precinct No. 4 is requesting consideration and action to award and enter into construction contracts with:
1. The 5125 Company for base bid and Alternate No.’s 1-7 for a total amount of $339,144.45 and;
2. Saenz Utility Contractors, Ltd. for Alternate No. 9 for a total amount of $40,000.00
For a HUD CDBG-R Fike Pump Structure - Flood drainage improvements project. Funds available through Year 22 (2009) CDBG-R flood drainage improvement and FY 23 (2010) flood drainage improvements.
1. The 5125 Company for base bid and Alternate No.’s 1-7 for a total amount of $339,144.45 and;
2. Saenz Utility Contractors, Ltd. for Alternate No. 9 for a total amount of $40,000.00
For a HUD CDBG-R Fike Pump Structure - Flood drainage improvements project. Funds available through Year 22 (2009) CDBG-R flood drainage improvement and FY 23 (2010) flood drainage improvements.
BACKGROUND
Bids were received and opened at the Hidalgo County – Purchasing Department on January 25, 2012. After review of bid tabulations, Raul Sesin P.E., C.F.M recommended that the base bid and alternates 1-7 be completed by The 5125 Company and Alternate 9 be completed by Saenz Utility Contractors, Ltd as the lowest of three (3) bidders. (See attached recommendation letter from the Raul Sesin, P.E., C.F.M. and copy of the bid tabulation.)
Funds Available: $156,588.60 Year 22 (2009) CDBG-R Precinct No. 4 – Flood Drainage Improvements
Precinct No. 4 funds: $278,234.44 Year 23 (2010) Precinct No. 4 – Flood Drainage Improvements
Total: $434,823.04
| Contractors | Contract Amounts: |
| The 5125 Company | $339,144.45 |
| Saenz Utility Contractor's Ltd. | $40,000.00 |
| Total: | $379,144.45 |
Funds Available: $156,588.60 Year 22 (2009) CDBG-R Precinct No. 4 – Flood Drainage Improvements
Precinct No. 4 funds: $278,234.44 Year 23 (2010) Precinct No. 4 – Flood Drainage Improvements
Total: $434,823.04
Fiscal Impact
- FISCAL YEAR:
- ACCT. #:
- Urban County Funds
- FUNDS AVAILABLE Y/N?:
- MATCHING FUNDS Y/N?:
BUDGETARY IMPACT:
Urban County Year 22 (2009) CDBG-R Precinct #4 Flood Drainage Improvement Funds and Year 23 (2010) Precinct #4 Flood Drainage Improvement Funds will be utilized for the Precinct #4 HUD CDBG-R Fike Pump Structure Flood Drainage Improvement Project.Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Budget and Management | mmunoz | 02/15/2012 04:22 PM |
| Purchasing / Internal | Alejandro Garcia | 02/17/2012 03:51 PM |
- Form Started By:
- Melissa Flores
- Started On:
- 02/15/2012 03:58 PM
- Final Approval Date:
- 02/17/2012