Information

CAPTION

Seeking approval of Change Order No. 1 with contractor Homero Alvarez dba Alvarez Construction for Morningside South Subdivision, Pct. No. 2 reflecting an additional 101 calendar days to contract time due to rain days and the acquisition of Hidalgo County Crossing Permit and Hidalgo County Irrigation District #2 Permit and the coordination with Irrigation District operations as submitted through project engineer SAM Engineering and Surveying, Inc. (C-CAP-11-022-03-07).

BACKGROUND


Fiscal Impact

FISCAL YEAR:
12
ACCT. #:
2-1312-431-00-122-900-0-XXX
FUNDS AVAILABLE Y/N?:
Y
MATCHING FUNDS Y/N?:
N

BUDGETARY IMPACT:

No Fiscal Impact to PO# 660987. Change order is for an increase of 101 calendar days to the overall project duration.

Attachments

Form Review

Inbox Reviewed By Date
Purchasing / Internal msalazar 04/11/2012 03:21 PM
Budget and Management mmunoz 04/11/2012 03:23 PM
Auditor's Office Alejandro Garcia 04/13/2012 04:26 PM
Form Started By:
yislas
Started On:
04/10/2012 11:11 AM
Final Approval Date:
04/13/2012