CAPTION
Consideration and approval to:
1. Increase the number of calendar days allotted in the Pct. 1 Catarina Subdivision Street and Drainage Improvements Project Construction Service Contract awarded to SASCON, Inc. by sixty (60) days for a total of 150 days, through a Change Order Request,
2. Submit Construction Contract Change Order No. 2 to the General Land Office (GLO) Contract No. 10-5066-000-5043 (formerly TDRA DRS010068), regarding the Pct. 1 Catarina Subdivision Street & Drainage Improvements Project.
3. Authorize the County Judge to sign any and all documents associated with Change Orders and/or Amendments pertaining to GLO Contract No. 10-5066-000-5043.
1. Increase the number of calendar days allotted in the Pct. 1 Catarina Subdivision Street and Drainage Improvements Project Construction Service Contract awarded to SASCON, Inc. by sixty (60) days for a total of 150 days, through a Change Order Request,
2. Submit Construction Contract Change Order No. 2 to the General Land Office (GLO) Contract No. 10-5066-000-5043 (formerly TDRA DRS010068), regarding the Pct. 1 Catarina Subdivision Street & Drainage Improvements Project.
3. Authorize the County Judge to sign any and all documents associated with Change Orders and/or Amendments pertaining to GLO Contract No. 10-5066-000-5043.
BACKGROUND
The requested time extension is due to delays associated with requests by the Irrigation District regarding the re-grading of the drainage ditch and issues related to the Contractor and Sub-Consultant agreement procedure. Please see attached letter from the project engineer, SAMES Engineering, and change order request data.
Fiscal Impact
- FISCAL YEAR:
- ACCT. #:
- FUNDS AVAILABLE Y/N?:
- MATCHING FUNDS Y/N?:
BUDGETARY IMPACT:
Urban County funds will be utilized for this project.Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Budget and Management | mmunoz | 04/25/2012 03:36 PM |
| Auditor's Office | aduran | 05/03/2012 09:19 AM |
| Purchasing / Internal | msalazar | 05/03/2012 01:30 PM |
- Form Started By:
- Melissa Flores
- Started On:
- 04/25/2012 02:54 PM
- Final Approval Date:
- 05/03/2012