4.
DRAINAGE DISTRICT
- Meeting Date:
- 04/03/2007
- Submitted For:
- Sylvia Sanchez
- Submitted By:
- Jaime Salazar, DRAINAGE DISTRICT
- Department:
- DRAINAGE DISTRICT
Information
CAPTION
A.) Approval of MOU between Hidalgo County Drainage District No. 1 and North Alamo Water Supply Corporation as it relates to Reverse Osmosis Facility Water Plant 1&4.
B.) Requesting approval of Change Order # 2 for the "North San Juan Lateral Channel Crossing Improvements-Minnesota Crossing" ( DD-06-023-09-19) for supplies added to the project in the amount of $11,149.82.
Project Engineer: R. Gutierrez Engineering Corporation
Contractor: Summit Contracting LTD.
C.) Approval of Budget Amendment to transfer out of General Fund $14,231.95 to fund the change orders of the above mentioned project.
B.) Requesting approval of Change Order # 2 for the "North San Juan Lateral Channel Crossing Improvements-Minnesota Crossing" ( DD-06-023-09-19) for supplies added to the project in the amount of $11,149.82.
Project Engineer: R. Gutierrez Engineering Corporation
Contractor: Summit Contracting LTD.
C.) Approval of Budget Amendment to transfer out of General Fund $14,231.95 to fund the change orders of the above mentioned project.