Requesting acceptance and approval of Change Order No.2 with increase in the amount of $5,705.40 and increase total days of (93) calendar days, with Saenz Utility Contractor, Ltd (#C-11-044A-06-28) contracted vendor for "Tower Road Phase I Project", reason for extension: unable to start work due to storm sewer system being installed (83 days) and another (10) due to inclement weather, with authority for County Judge or Court Member to execute document.

BACKGROUND


Fiscal Impact

FISCAL YEAR:
2012
ACCT. #:
2-1200-431-00-122-049-0-731
FUNDS AVAILABLE Y/N?:
Y
MATCHING FUNDS Y/N?:

BUDGETARY IMPACT:

PO #662863 available balance of $177,404.97

** available account balance of $95,859.50 as of 5/30/2012.

*** New contract time is 243 days


Attachments

Form Review

Inbox Reviewed By Date
Budget and Management mmunoz 05/30/2012 04:39 PM
Purchasing / Internal Monica Salinas 06/08/2012 05:02 PM
Form Started By:
ycisneros
Started On:
05/24/2012 11:29 AM
Final Approval Date:
06/08/2012