Seeking approval of Change Order No. 1 with contractor Asago LLC dba Asago Construction for Mid Valley Estates Subdivision, Pct. No. 1 reflecting a net increase of $685.00 due to quantitative adjustments as submitted through project engineer TEDSI Infrastructure Group (C-CAP-12-049-05-01).
BACKGROUND
Fiscal Impact
- FISCAL YEAR:
- 2
- ACCT. #:
- 2-1312-431-00-121-461-0-73X
- FUNDS AVAILABLE Y/N?:
- Y
- MATCHING FUNDS Y/N?:
BUDGETARY IMPACT:
P.O.#679223 for Asago, LLC d/b/a Asago Construction. Funds available as of 9-7-12 to fund Change Order #1.Original contract amount - $327,181.08
Change Order #1 increase- $685.00
Revised Contract amount- $327,866.08
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Purchasing / Internal | msalazar | 09/07/2012 11:29 AM |
| Budget and Management | mmunoz | 09/07/2012 11:34 AM |
| Auditor's Office | Monica Salinas | 09/07/2012 05:07 PM |
- Form Started By:
- mjackson
- Started On:
- 09/05/2012 07:45 AM
- Final Approval Date:
- 09/07/2012