Skip to main content

AgendaQuick™

View Agenda Item

AI- 35291
7.E.
CC CONSENT
Meeting Date:
11/27/2012
Submitted For:
Martha L. Salazar
Submitted By:
Rocio Villarreal, PURCHASING DEPT.
Department:
PURCHASING DEPT.

Information

CAPTION

Approval of Request for Payment-Application No. 9 R1 in the amount of $317,952.41 from D. Wilson Construction Co. awarded contractor for the, "Construction of the Sheriff's Office Substation in the Pct 1 Area", and as certified for payment by project architect, Gignac & Associates-C-11-032-01-20.

BACKGROUND


Fiscal Impact

FISCAL YEAR:
2012
ACCT. #:
2-13XX-423-00-280-036-0-7XX
FUNDS AVAILABLE Y/N?:
Y
MATCHING FUNDS Y/N?:

BUDGETARY IMPACT:

PO# 670920 available balance as of 11-21-12 $594,884.85 for D. Wilson Construction Co.

Available balance by Account number:

2-1336-423-00-280-036-0-720 $431,321.00
2-1342-423-00-280-036-0-739 $ 163,563,85

Attachments

Form Review

Inbox Reviewed By Date
Purchasing / Internal msalazar 11/19/2012 02:59 PM
Budget and Management mmunoz 11/19/2012 03:18 PM
Auditor's Office Alejandro Garcia 11/21/2012 04:10 PM
Form Started By:
Rocio Villarreal
Started On:
11/14/2012 04:52 PM
Final Approval Date:
11/21/2012