AI- 40666
Purchasing Department 9.H.
CC CONSENT
- Meeting Date:
- 09/17/2013
- Submitted For:
- Commissioner Hector Palacios
- Submitted By:
- Erika Zamora, COMM. PCT. #2
- Department:
- COMM. PCT. #2
Information
CAPTION
Acceptance and approval of Change Order No.1 reflecting an increase of $3,750.00 for one manhole adjustment and relocation of two existing sewer clean-outs with contractor 2GS, L.L.C. for the Pct. 2 Little Mexico/S Tower Estates Paving and Drainage Project, as submitted through project engineer Raul Sesin (C-13-127-05-21).
BACKGROUND
Fiscal Impact
- FISCAL YEAR:
- 2013
- ACCT. #:
- 3-1200-431-00-122-088-0-731
- FUNDS AVAILABLE Y/N?:
- Y
- MATCHING FUNDS Y/N?:
- N
BUDGETARY IMPACT:
Funds available as of 9/11/13 $30,563.99.Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Purchasing / Internal | msalazar | 09/13/2013 11:18 AM |
| Budget and Management | Obdett Calzada | 09/13/2013 02:00 PM |
| Auditor's Office | Monica Salinas | 09/13/2013 06:07 PM |
- Form Started By:
- Erika Zamora
- Started On:
- 09/11/2013
- Final Approval Date:
- 09/13/2013