CAPTION
Approval of the following with 2GS, Inc. for the Little Mexico Subdivision and South Tower Estates project, as submitted and recommended by project engineer, Raul Sesin, PE for contract # C-13-127-05-21:
1. Application for Final Payment in the amount of $148,192.12;
2. Application for Retainage in the amount of $23,615.98;
3. Certificate of Construction Completion reflecting the date of October 30, 2013.
1. Application for Final Payment in the amount of $148,192.12;
2. Application for Retainage in the amount of $23,615.98;
3. Certificate of Construction Completion reflecting the date of October 30, 2013.
BACKGROUND
Fiscal Impact
- FISCAL YEAR:
- 2013
- ACCT. #:
- 3-1200-431-00-122-088-0-731
- FUNDS AVAILABLE Y/N?:
- Y
- MATCHING FUNDS Y/N?:
- N
BUDGETARY IMPACT:
Funding Available through PO# 694655.- FISCAL YEAR:
- 2013
- ACCT. #:
- 3-1200-206-00-122-030-0-000
- FUNDS AVAILABLE Y/N?:
- Y
- MATCHING FUNDS Y/N?:
- N
BUDGETARY IMPACT:
Account currently reflects a balance $15,816.40, however, after application for payment #3 is processed the retainage account will reflect a balance of $23,615.98.Attachments
- Application for Payment No. 3 (Final Payment)
- Application for Payment No. 4 (Ret Release)
- Certificate of Completion
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Purchasing / Internal | msalazar | 12/12/2013 04:34 PM |
| Budget and Management | Debbie Tamez | 12/12/2013 04:44 PM |
| Auditor's Office | Monica Salinas | 12/17/2013 09:12 AM |
- Form Started By:
- Clarissa Jasso
- Started On:
- 12/11/2013 01:31 PM
- Final Approval Date:
- 12/17/2013