AI- 43250
Purchasing Department 9.E.
CC CONSENT
- Meeting Date:
- 03/05/2014
- Submitted For:
- Comm. Joe Flores, Pct. #3
- Submitted By:
- Marcie Jackson, COMM. PCT. #1
- Department:
- COMM. PCT. #1
Information
CAPTION
Seeking ratification of fully executed Change Order No. 1 reflecting an additional 21 calendar days due to rain days with contractor Castle Enterprises, LLC for Randolph Barnett #1 Subdivision, Pct. No. 3 as submitted though project engineer Javier Hinojosa Engineering (C-CAP-13-191-07-30).
BACKGROUND
Fiscal Impact
- FISCAL YEAR:
- 2014
- ACCT. #:
- 4-1312-431-00-123-600-0-733/731
- FUNDS AVAILABLE Y/N?:
- Y
- MATCHING FUNDS Y/N?:
- N
BUDGETARY IMPACT:
No Fiscal Impact.Attachments
- Change Order No.1 Randolph Barnett Subdivision No.1
- Executed Contract Randolph Barnett Subdivision No.1
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Purchasing / Internal | msalazar | 02/26/2014 02:07 PM |
| Budget and Management | Debbie Tamez | 02/26/2014 02:50 PM |
| Auditor's Office | Monica Salinas | 02/28/2014 05:19 PM |
- Form Started By:
- mjackson
- Started On:
- 02/19/2014 03:13 PM
- Final Approval Date:
- 02/28/2014