Right of Way: * North Alamo Water Supply Corporation:
1. San Marcos Subdivision: Bore Alberta Road- from centerline to Valverde Rd (FM 1423) go west 3,200 feet. Will bore Alberta Road from North to South for an 8" waterline with a 16" PVC casing.
2. San Joaquin Subdivision Phase II: Bore Minnesota Road- from centerline of Valverde Road (FM 1423) go east 625 feet. Will bore Minnesota Road from North to South using a 16" PVC casing. Will tie into a 12" waterline. Bore Minnesota Road- from centerline of Valverde Road (FM 1423) go east 1,375 feet. Will bore Minnesota Road from North to South using a 16" PVC casing. Will tie into a 12" waterline.
M.E. Alaniz Subdivision: Bore Terry Road- from centerline of Benito Ramirez Road go North 300 feet. Will bore Terry Road from West to East using a 2" PVC casing. Will tie into an 8" waterline.
D. Flores Subdivision: 1. Bore Mile 14 1/2- from centerline of FM 491 go West 430 feet. Will bore Mile 14 1/2 from North to South with a 2" PVC casing for an 1" water service. Will tie into a 4" waterline. 2. Bore Mile 14 1/2- from centerline of FM 491 go West 820 feet. Will bore Mile 14 1/2 from North to South with a 2" PVC casing for an 1" water service. Will tie into a 4" waterline.
Magdalena Estates Subdivision: 1. Bore Tower Road- from centerline of Wisconsin Road go South 50 feet. Will bore Tower Road from West to East a 16" PVC casing for an 8" waterline. Will tie into a 12" waterline. 2. Bore Tower Road- from centerline of Wisconsin Road go South 440 feet. Will bore Tower Road from West to East a 2" PVC casing for a 1" water service. Will tie into a 12" waterline. 3. Bore Tower Road- from centerline of Wisconsin Road go South 640 feet. Will bore Tower Road from West to East a 2" PVC casing for a 1" water service. Will tie into a 12" waterline. 4. Bore Tower Road- from centerline of Wisconsin Road go South 840 feet. Will bore Tower Road from West to East a 2" PVC casing for a 1" water service. Will tie into a 12" waterline. 5. Bore Tower Road- from centerline of Wisconsin Road go South 1,030 feet. Will bore Tower Road from West to East a 2" PVC casing for a 1" water service. Will tie into a 12" waterline. 6. Bore Tower Road- from centerline of Wisconsin Road go South 1,230 feet. Will bore Tower Road from West to East a 2" PVC casing for a 1" water service. Will tie into a 12" waterline.
1. San Marcos Subdivision: Bore Alberta Road- from centerline to Valverde Rd (FM 1423) go west 3,200 feet. Will bore Alberta Road from North to South for an 8" waterline with a 16" PVC casing.
2. San Joaquin Subdivision Phase II: Bore Minnesota Road- from centerline of Valverde Road (FM 1423) go east 625 feet. Will bore Minnesota Road from North to South using a 16" PVC casing. Will tie into a 12" waterline. Bore Minnesota Road- from centerline of Valverde Road (FM 1423) go east 1,375 feet. Will bore Minnesota Road from North to South using a 16" PVC casing. Will tie into a 12" waterline.
M.E. Alaniz Subdivision: Bore Terry Road- from centerline of Benito Ramirez Road go North 300 feet. Will bore Terry Road from West to East using a 2" PVC casing. Will tie into an 8" waterline.
D. Flores Subdivision: 1. Bore Mile 14 1/2- from centerline of FM 491 go West 430 feet. Will bore Mile 14 1/2 from North to South with a 2" PVC casing for an 1" water service. Will tie into a 4" waterline. 2. Bore Mile 14 1/2- from centerline of FM 491 go West 820 feet. Will bore Mile 14 1/2 from North to South with a 2" PVC casing for an 1" water service. Will tie into a 4" waterline.
Magdalena Estates Subdivision: 1. Bore Tower Road- from centerline of Wisconsin Road go South 50 feet. Will bore Tower Road from West to East a 16" PVC casing for an 8" waterline. Will tie into a 12" waterline. 2. Bore Tower Road- from centerline of Wisconsin Road go South 440 feet. Will bore Tower Road from West to East a 2" PVC casing for a 1" water service. Will tie into a 12" waterline. 3. Bore Tower Road- from centerline of Wisconsin Road go South 640 feet. Will bore Tower Road from West to East a 2" PVC casing for a 1" water service. Will tie into a 12" waterline. 4. Bore Tower Road- from centerline of Wisconsin Road go South 840 feet. Will bore Tower Road from West to East a 2" PVC casing for a 1" water service. Will tie into a 12" waterline. 5. Bore Tower Road- from centerline of Wisconsin Road go South 1,030 feet. Will bore Tower Road from West to East a 2" PVC casing for a 1" water service. Will tie into a 12" waterline. 6. Bore Tower Road- from centerline of Wisconsin Road go South 1,230 feet. Will bore Tower Road from West to East a 2" PVC casing for a 1" water service. Will tie into a 12" waterline.
BACKGROUND
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Budget and Management | Veronica Ortiz | 10/17/2014 02:10 PM |
| Auditor's Office | Monica Salinas | 10/24/2014 06:15 PM |
- Form Started By:
- Rebecca Gomez
- Started On:
- 10/14/2014 02:41 PM
- Final Approval Date:
- 10/24/2014