CAPTION
Requesting approval for a six (6) month extension to the FY 2008 and FY 2012 Community Housing Development Organization (CHDO) Agreement between the Urban County Program and Proyecto Azteca
BACKGROUND
Proyecto Azteca is contractually obligated to produce five (5) units that will be sold to qualified homebuyers. Currently, three (3) units have been successfully completed and two (2) other units are under construction. Unfortunately, there is a drainage issue on one of the properties that has not allowed for the placement of the newly constructed home. Proyecto Azteca has been in contact with Hidalgo County Drainage District No 1 Director, Mr. Raul Sesin, who advised against placing a housing unit on the particular property. The CHDO is assisting the family in locating another lot and has also hired a real estate agent for assistance. The CHDO has requested an extension to complete the sale of the units under this contract. The UCP is recommending an additional six (6) month extension for the completion and final loan closing for these pending units.
| CHDO Name | Fiscal Year | Amount | Contract Date | Contract Exp. | New Contract Exp. |
| Proyecto Azteca | 2008 and 2012 | $ 297,429.90 | June 17, 2014 | August 31, 2015 | February 29, 2016 |
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Budget and Management | Veronica Ortiz | 09/02/2015 02:11 PM |
| Purchasing / Internal | Monica Salinas | 09/11/2015 06:02 PM |
- Form Started By:
- sregalado
- Started On:
- 08/26/2015 05:01 PM
- Final Approval Date:
- 09/11/2015