DRAINAGE DISTRICT
Meeting Date:
01/05/2016
Submitted By:
Claudette Guerrero, DRAINAGE DISTRICT
Department:
DRAINAGE DISTRICT

Information

CAPTION

2013 Bonds:
Pct.4 Rural Drainage Development

A. Request approval to issue manual payment for Application for Payment No. 3 in the amount of $99,587.70 from PEGA JPS Utilities, LLC related to Construction Contract No. HCDD1-15-010-07-22B-Pct.4 Tower Road & Mile 17 1/2 Road Area Drainage Improvements.

Project Engineer: Jose N. Saldivar, P.E.-Hidalgo County Drainage District No. 1
PO#627525

B. Acceptance of Certificate of Substantial Completion from PEGA JPS Utilities, LLC for Construction Project HCDD1-15-010-07-22B-Pct.4 Tower Road & Mile 17 1/2 Area Drainage Improvement.

Project Engineer: Jose N. Saldivar, P.E.-Hidalgo County Drainage District No. 1
PO#627525.

BACKGROUND

Substantial Completion: 12-22-2015 

Fiscal Impact

Attachments

Form Review

Inbox Reviewed By Date
Budget and Management Veronica Ortiz 12/22/2015 04:02 PM
Final Approval Monica Salinas 01/01/2016 01:03 PM
Form Started By:
ccavazos
Started On:
12/22/2015 01:21 PM
Final Approval Date:
01/01/2016