CAPTION

Requesting approval of Certificate of Construction Completion submitted by project engineer TEDSI Infrastructure Group reflecting the completion date of August 20, 2007 for La Blanca Heights Subdivision with contractor Sascon Inc. C-CAP-07-017-05-01.

BACKGROUND

Presentation for discussion, consideration, acceptance, and approval of Request for Application for Payment No 2 (Release of Retainage) in the amount of $6,715.15, from Sascon Inc., contracted vendor for  Road & Drainage Construction of La Blanca Heights Subdivision  submitted by project engineer Tedsi Infrastructure Group. C-CAP-07-017-05-01. PREVIOUSLY APPROVED IN COMMISSIONER'S COURT ON 9/4/07

Fiscal Impact

FISCAL YEAR:
2007
ACCT. #:
7-1311-431-00-121-368-0-733/734
FUNDS AVAILABLE Y/N?:
Y
MATCHING FUNDS Y/N?:

BUDGETARY IMPACT:

Request for Application for Payment No 2 (Release of Retainage) in the amount of $6,715.15 was approved in CC on 9/4/07.
Available Balance in PO #589117 in object code 733 $17,485.07 as of 9-12-07
Available Balance in PO #589117 in object code 734 $49,666.43 as of 9-12-07

Attachments

Form Review

Inbox Reviewed By Date
Purchasing / Internal msalazar 09/12/2007 12:25 PM
Budget and Management Dina Trevino 09/12/2007 01:29 PM
Auditor's Office 09/14/2007 05:14 PM
Form Started By:
lmoya
Started On:
09/12/2007 11:26 AM
Final Approval Date:
09/14/2007