Presentation for discussion, consideration and action on a recommendation by project engineer TEDSI Infrastructure Group to award to the lowest bidder meeting all specifications for the following bids subject to TXDOT approval:
1. CAP-07-027-08-29 Road & Drainage Construction of RC Babb I Subdivision(s)
2. CAP-07-028-08-29 Road & Drainage Construction of RC Babb II Subdivision(s)
3. CAP-07-029-08-29 Road & Drainage Construction of RC Babb III Subdivision(s)
BACKGROUND
Fiscal Impact
- FISCAL YEAR:
- 2007
- ACCT. #:
- 7-1311-431-00-121-575-0-734
- FUNDS AVAILABLE Y/N?:
- Y
- MATCHING FUNDS Y/N?:
BUDGETARY IMPACT:
Available Balance as of 9-20-07 $28,459.20.- FISCAL YEAR:
- 2007
- ACCT. #:
- 7-1311-431-00-121-576-0-734
- FUNDS AVAILABLE Y/N?:
- Y
- MATCHING FUNDS Y/N?:
BUDGETARY IMPACT:
Available Balance as of 9-20-07 $56,017.92.
- FISCAL YEAR:
- 2007
- ACCT. #:
- 7-1311-431-00-121-577-0-734
- FUNDS AVAILABLE Y/N?:
- Y
- MATCHING FUNDS Y/N?:
BUDGETARY IMPACT:
Available Balance as of 9-20-07 $18,207.84.
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Purchasing / Internal | msalazar | 09/19/2007 05:10 PM |
| Budget and Management | Damaris San Miguel | 09/20/2007 09:40 AM |
| Auditor's Office | 09/21/2007 05:22 PM |
- Form Started By:
- lmoya
- Started On:
- 09/19/2007 02:23 PM
- Final Approval Date:
- 09/21/2007