CAPTION
Approval to execute AIA Document A101 awarded by CC on 09/11/07 for the "Construction Multipurpose Facility at South Tower Park," and to authorize project architect, VA Architecture, to issue and forward "Notice to Proceed" to contractor, Rio Valley Construction, Inc.
BACKGROUND
refer to AI 5430 CC 9-11-07 17.D.1
Fiscal Impact
- FISCAL YEAR:
- 2007
- ACCT. #:
- 7-1334-452-00-122-022-0-720
- FUNDS AVAILABLE Y/N?:
- Y
- MATCHING FUNDS Y/N?:
BUDGETARY IMPACT:
Available Balance as of 9-20-07 $500,000.00. The remaining funding will be contributed by WIC, Urban County and a Tax Note to be received in October 2007. Total project cost is $1,468,000.00 (refer to attachment, and AI 5430 CC 9-11-07)Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Purchasing / Internal | msalazar | 09/19/2007 05:20 PM |
| Budget and Management | Damaris San Miguel | 09/20/2007 09:48 AM |
| Dina Trevino | 09/21/2007 05:22 PM |
- Form Started By:
- Rocio Villarreal
- Started On:
- 09/19/2007 03:53 PM
- Final Approval Date:
- 09/21/2007