CAPTION
Engineering Firm: Tedsi Infrastructure Group
2013 Bonds
Budget: 370-Control Structures
A. Invoice No. 20162838 in the amount of $6,153.15 related to Work Authorization No. 4A-Monte Cristo Drain Control Structure.
PO#626349 & 623103
B. Invoice No. 20162839 in the amount of $2,085.66 related to Work Authorization No. 4B-Weslaco North Lateral Control Structure.
PO#626348 & 623104
2013 Bonds
Budget: 370-Control Structures
A. Invoice No. 20162838 in the amount of $6,153.15 related to Work Authorization No. 4A-Monte Cristo Drain Control Structure.
PO#626349 & 623103
B. Invoice No. 20162839 in the amount of $2,085.66 related to Work Authorization No. 4B-Weslaco North Lateral Control Structure.
PO#626348 & 623104
BACKGROUND
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Final Approval | Monica Salinas | 09/23/2016 06:02 PM |
- Form Started By:
- ccavazos
- Started On:
- 09/23/2016 10:18 AM
- Final Approval Date:
- 09/23/2016