A. Certificate of Substantial Completion as Submitted by ASAGO LLC for Paving & Drainage Improvements for Mile 2 1/2 East Road;
B. Application for Payment No.5 (final) as submitted by ASAGO LLC in the amount of $8,712.00 for the provision of Paving & Drainage Improvements for Mile 2 1/2 East Road under contract C-16-363-11-01.

BACKGROUND

Pct.1 / FEMA Road & Drainage Improvements Project - Mile 2 1/2 East Road PO#753760.

Fiscal Impact

CALENDAR YEAR:
2017
ACCT. #:
7-1280-431-00-121-811-5-721
FUNDS AVAILABLE Y/N?:
Y
MATCHING FUNDS Y/N?:

BUDGETARY IMPACT:

Funding available through PO# 753760.

Attachments

Form Review

Inbox Reviewed By Date
Purchasing / Internal msalazar 05/09/2017 03:02 PM
Budget and Management Veronica Ortiz 05/09/2017 03:11 PM
Final Approval Monica Salinas 05/12/2017 05:46 PM
Form Started By:
ndelosrios
Started On:
05/09/2017 01:16 PM
Final Approval Date:
05/12/2017