CAPTION

Requesting approval of the following for 2GS, LLC dba Earthworks Enterprise for FEMA Road & Drainage Improvements: Mile 11 North, Mile 13 ½ & Yvette Circle under Contract C-16-398-12-13:
A. Requesting acceptance and approval of Certificate of Substantial Completion by 2GS, LLC, dba Earthworks Enterprise, as submitted and recommended by project engineer LeFevre Engineering & Management Consulting, LLC reflecting the date of May 10, 2017.
B. Application for Payment No. 2 (Final) in the amount of $319,802.69.

BACKGROUND

FEMA Mile 11 North Rd. - PO # 757346
Mile 13 1/2 North Rd. - PO # 757345
Yvette Circle. - PO # 757524

Fiscal Impact

CALENDAR YEAR:
2017
ACCT. #:
7-1280-431-11-121-81X-5-721
FUNDS AVAILABLE Y/N?:
Y
MATCHING FUNDS Y/N?:

BUDGETARY IMPACT:


Accounts:

7-1280-431-11-121-817-5-721 - PCT1-00090-MILE 13 1/2 RD-ROADS - PO #757345
7-1280-431-11-121-818-5-721 - PCT1-00090-MILE 11-ROADS - PO #757346

7-1280-431-11-121-819-5-721 - PCT1-00090-YVETTE CIRCLE-ROADS - PO #757524
Funds available as of 5-12-17 in all above POs.


CALENDAR YEAR:
2017
ACCT. #:
7-1200-431-11-121-819-5-721
FUNDS AVAILABLE Y/N?:
Y
MATCHING FUNDS Y/N?:

BUDGETARY IMPACT:

Funds available as of 5-12-17; a PO increase will be submitted by Pct. 1 in order to fully fund payment request (including retainage).

Attachments

Form Review

Inbox Reviewed By Date
Purchasing / Internal msalazar 05/12/2017 11:30 AM
Budget and Management Veronica Ortiz 05/12/2017 11:33 AM
Final Approval Monica Salinas 05/12/2017 05:46 PM
Form Started By:
Erica Espinosa
Started On:
05/11/2017 04:17 PM
Final Approval Date:
05/12/2017