Skip to main content

AgendaQuick™

View Agenda Item

AI- 59856
Purchasing Department   20.E.2.
CC - REGULAR
Meeting Date:
05/16/2017
Submitted For:
Marty Salazar
Submitted By:
Letty Saenz, PURCHASING DEPT.
Department:
PURCHASING DEPT.

Information

CAPTION

Requesting approval of SA1 to WA 2,  for the increased amount of ($ 58,831.00) amending Exhibit C-Work Schedule & Estimated Man-hour Breakdown) with change to estimated original cost under WA 2 from ($ 1,067,000.00) to ($ 1,125,831.00), as submitted by L&G Consulting Engineers, Inc. d/b/a L&G Engineering in connection to agreement # C-13-178-08-20 for "Job Specific Project"- Engineering Services required for Right-of-Way Acquisition, Compensable Utility Management Oversight for the FM 2220 (Ware Road) project from Mile 3 N (FM 1924) to Mile 5 N (FM 676 )located within Hidalgo County Precinct No. 4.

BACKGROUND

SA1-WA2-C-13-178-08-20 -L&G Engineering -Pct 4

Fiscal Impact

CALENDAR YEAR:
2017
ACCT. #:
7-1200-431-00-124-007-0-334
FUNDS AVAILABLE Y/N?:
Y/pend
MATCHING FUNDS Y/N?:

BUDGETARY IMPACT:

Refer to AI-59864 transfer

Attachments

Form Review

Inbox Reviewed By Date
Purchasing / Internal msalazar 05/12/2017 02:28 PM
Budget and Management Veronica Ortiz 05/12/2017 02:30 PM
Final Approval Monica Salinas 05/12/2017 05:46 PM
Form Started By:
Letty Saenz
Started On:
05/12/2017 01:43 PM
Final Approval Date:
05/12/2017