Skip to main content

AgendaQuick™

View Agenda Item

AI - 60536
7.
DRAINAGE DISTRICT
Meeting Date:
07/11/2017
Submitted For:
Lora Briones
Submitted By:
Claudette Guerrero, DRAINAGE DISTRICT
Department:
DRAINAGE DISTRICT

Information

CAPTION

Request approval of the following items after review and audit procedures are complete:
A. Change Order No. 4 in the amount of $(14,966.00) pertaining to Construction Contract No. HCDD1-16-006-04-26 J09 Drain Improvements Phase II and addition of 126 Contract Days.
B. Certificate of Construction Completion from Texas Cordia Construction, LLC pertaining to Construction Contract No. HCDD1-16-006-04-26 J09 Drain Improvement Phase II.
C. Application for Payment No. 7-Retainage Release in the amount of $74,431.74 from Texas Cordia Construction, LLC pertaining to Construction Contract No. HCDD1-16-006-04-26 J09 Drain Improvements Ph. II.
Project Engineer: Tedsi Infrastructue Group
PO#629475

BACKGROUND


Fiscal Impact

Attachments

Form Review

Inbox Reviewed By Date
Final Approval Monica Salinas 07/07/2017 04:28 PM
Form Started By:
ccavazos
Started On:
06/29/2017 04:51 PM
Final Approval Date:
07/07/2017