CAPTION
BCAP/Pct. 3
Requesting Acceptance and Approval of Application for Payment No. 3 (Retainage Release) in the amount of $21,953.22 submitted by Castle Enterprises awarded contractor for Pct. 3 El Paraiso Sub. as certified by project engineer Javier Hinojosa Engineering under Contract# C-CAP-17-124-05-16.
A. Certificate of Construction Completion as submitted and recommended by Project Engineer, Javier Engineering.
B. Application for Payment No. 3 (Retainage Release) in the amount of $21,953.22
Requesting Acceptance and Approval of Application for Payment No. 3 (Retainage Release) in the amount of $21,953.22 submitted by Castle Enterprises awarded contractor for Pct. 3 El Paraiso Sub. as certified by project engineer Javier Hinojosa Engineering under Contract# C-CAP-17-124-05-16.
A. Certificate of Construction Completion as submitted and recommended by Project Engineer, Javier Engineering.
B. Application for Payment No. 3 (Retainage Release) in the amount of $21,953.22
BACKGROUND
Fiscal Impact
- CALENDAR YEAR:
- 2017
- ACCT. #:
- 7-1312-206-00-000-054-0-000
- FUNDS AVAILABLE Y/N?:
- y
- MATCHING FUNDS Y/N?:
- y
BUDGETARY IMPACT:
BCAP/Pct. 3REQ# 345165 PO# 764461
Attachments
- Appl. for Pmt. No. 3 Retainage - Castle
- Cert. of Const. Completion - Castle Enterprises (El Paraiso)
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Final Approval | Monica Salinas | 01/05/2018 05:50 PM |
- Form Started By:
- ndelosrios
- Started On:
- 01/05/2018 09:10 AM
- Final Approval Date:
- 01/05/2018