Approval of the following items for Synergy Builders of Texas for the Pct. 4- Recovery & Motor Pool Improvements Project, as submitted and recommended by project engineer, Trey Murray, PE- Halff Associates, Inc. for contract # C-17-067-03-21:
A. Application for Retainage release in the amount of $49,350.00;
B. Acceptance of Certificate of Construction Completion, reflecting the date of February 5, 2018.BACKGROUND
Substantial Completion approved by Commissioners' Court on 02-06-18 (AI-63598).
Fiscal Impact
- CALENDAR YEAR:
- ACCT. #:
- FUNDS AVAILABLE Y/N?:
- MATCHING FUNDS Y/N?:
BUDGETARY IMPACT:
Funding available pending budget carryover through po# 761124 .Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Purchasing / Internal | msalazar | 03/16/2018 02:50 PM |
| Budget and Management | Veronica Ortiz | 03/16/2018 03:28 PM |
| Final Approval | Monica Salinas | 03/16/2018 05:06 PM |
- Form Started By:
- lmayorga
- Started On:
- 03/16/2018 01:44 PM
- Final Approval Date:
- 03/16/2018