Skip to main content

AgendaQuick™

View Agenda Item

AI - 65110
3.
DRAINAGE - CONSENT
Meeting Date:
06/11/2018
Submitted For:
Jaime Salazar
Submitted By:
Moises Salazar, DRAINAGE DISTRICT
Department:
DRAINAGE DISTRICT

Information

CAPTION

Ratification of the fully executed Change Order No. 2, reflecting a decrease in the amount of $ -9,450.00, and an increase of 167 calendar days, in connection with the construction contract No. C-HCDD1-16-039-08-16 - Hidalgo County Drainage District No. 1 “Drainage Improvements Project Mercedes Lateral-Flood Pump” as recommended by project engineer, TEDSI Infrastructure Group, and approved by HCDD1 General Manager, Mr. Raul E. Sesin, P.E., C.F.M., subject to compliance with HB1295.

BACKGROUND


Fiscal Impact

Attachments

Form Review

Inbox Reviewed By Date
Final Approval Monica Salinas 06/07/2018 03:09 PM
Form Started By:
moysalazar
Started On:
05/30/2018 01:37 PM
Final Approval Date:
06/07/2018