AI - 65110
3.
DRAINAGE - CONSENT
- Meeting Date:
- 06/11/2018
- Submitted For:
- Jaime Salazar
- Submitted By:
- Moises Salazar, DRAINAGE DISTRICT
- Department:
- DRAINAGE DISTRICT
Information
CAPTION
Ratification of the fully executed Change Order No. 2, reflecting a decrease in the amount of $ -9,450.00, and an increase of 167 calendar days, in connection with the construction contract No. C-HCDD1-16-039-08-16 - Hidalgo County Drainage District No. 1 “Drainage Improvements Project Mercedes Lateral-Flood Pump” as recommended by project engineer, TEDSI Infrastructure Group, and approved by HCDD1 General Manager, Mr. Raul E. Sesin, P.E., C.F.M., subject to compliance with HB1295.
BACKGROUND
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Final Approval | Monica Salinas | 06/07/2018 03:09 PM |
- Form Started By:
- moysalazar
- Started On:
- 05/30/2018 01:37 PM
- Final Approval Date:
- 06/07/2018