CAPTION
Acceptance and approval of Change Order No. 1 with a "decrease" of <$7,498.62> from original contract price ($173,738.00) totaling ($166,239.38) as (submitted and recommended by project engineer Halff Associates, Inc.) for Hunt & Woodruff Construction Company, LLC in connection to ongoing project: "Conversion of Three (3) Existing Cells into Padded Security Cells at the Hidalgo County Jail" for the HC Sheriff's Office, Contract # 2017-301-TDL (PCA 3-100-14).
BACKGROUND
Change Order #1-Hunt & Woodruff (padded cells project)-2017-301-TDL
Fiscal Impact
- CALENDAR YEAR:
- ACCT. #:
- FUNDS AVAILABLE Y/N?:
- MATCHING FUNDS Y/N?:
BUDGETARY IMPACT:
Funding source Acct# 8-2102-423-21-280-015-0-430 (PO #774475) as provided by Sheriff's OfficeAttachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Final Approval | Monica Salinas | 09/01/2018 |
- Form Started By:
- Letty Saenz
- Started On:
- 08/29/2018 02:38 PM
- Final Approval Date:
- 09/01/2018